Schedule of condition of property
Contents |
[edit] Introduction
A schedule of condition (SOC) is a factual record of the condition of a property, normally prepared for legal or contractual reasons. Schedules of condition can be prepared for either residential or commercial buildings.
They create a complete record of the condition of the property on a particular date that can be used as a benchmark against which its condition can be assessed in the future and any changes identified.
Schedules of condition may be prepared under the instruction of a landlord, a tenant, an employer, a contractor, or a neighbour. Appointing an independent expert to prepare a schedule of condition should help to give it greater weight if there are subsequent claims or negotiations. It may be beneficial to seek agreement of the other party that the schedule is a fair reflection of the condition of the property when it is prepared.
It is important to recognise that identifying a change in the condition of a property does not necessarily attribute blame for that change.
[edit] Leases
For commercial or residential property leases, a schedule of condition can be required when a new lease is entered into to confirm the condition of the property. This ensures that the condition recorded so that any existing defects and their repair costs are identified prior to a commitment to lease being made, and can help with lease negotiation. It can also be used to establish responsibility for dilapidations and reinstatement, typically towards the end of a lease.
[edit] Construction
A schedule of conditions might be prepared before construction begins for adjacent properties or structures that will be retained, or if part of a building is being refurbished. This not only helps protect against potential claims from neighbours, who may only begin to notice pre-existing defects in their property when the noise and vibration of construction begins, but can also establish contractor liability for damage to the employer’s properties.
[edit] Party walls
For both commercial and residential properties, a schedule of condition can be prepared where the Party Wall etc. Act 1996 applies. This is to provide evidence of the condition of the neighbouring building prior to works beginning. The party wall surveyors can then undertake a re-inspection of the building and determine whether any damage has occurred and also what repairs should be carried out.
[edit] Contents
Typically, schedules of condition are prepared by surveyors and may comprise:
- The purpose of the schedule.
- Details of the location and extent of the property being assessed.
- A general description of the construction of the property.
- The time, date and weather conditions under which the inspection was made.
- Aspects of the property included in or excluded from the assessment.
- The purposes for which the schedule may be relied.
- Drawings of the property.
- Definitions (for example, ‘slight’, ‘moderate’ and ‘severe’).
- A written schedule setting out the location and nature of each item inspected (inside and out) and its condition and any other remarks. This will describe the overall condition and may identify existing issues, such as cracks, staining, holes, decay, discolouration, leaks and other defects, disrepair or deterioration
- Accompanying photographs and video.
- Specific tests that may have been carried out.
[edit] Related articles on Designing Buildings Wiki
- Betterment.
- Condition.
- Defects.
- Dilapidations.
- Homes (Fitness for Human Habitation) Act 2018.
- Mobilisation.
- Party wall act.
- Schedule.
- Schedule of defects.
- Schedule of dilapidations.
- Scott schedule.
- Supersession.
- Three party wall notice responses.
[edit] External references
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.
























Comments